# The State's new erosion mitigation project aims to protect the Spur Road from future flood events
- URL: https://ktna.org/the-states-new-erosion-mitigation-project-aims-to-protect-the-spur-road-from-future-flood-events/
- Published: 2026-11-19T00:23:46.000Z
- Updated: 2026-11-19T00:23:46.000Z
- Description: This work will take place Monday through Sunday from 6 am to 6 pm until December 15th.
- Author: Marion Chesterton
- Tags: Local News, News

Last week, Alaska’s Department of Transportation started an emergency project near the railroad crossing in Talkeetna to mitigate immediate erosion concerns. The state agency plans to dig a 750-foot-long trench along the roadway, fill it with riprap, backfill it, and then grade and stabilize the area. 

The state’s Regional Hydraulics Engineer, Orion LeCroy, says twenty to fifty feet of bank near the Talkeetna Spur Road was lost over a three-year span leading up to spring 2026\. During last July’s flood event, an extra twenty to forty feet of bank was lost. Only 70 feet remain between the river and the pavement's edge. 

DOT is using Class 3 riprap from Portage to armor the area against future flood events. 

According to Justin Shelby, the state’s Administrative Operations Manager for the Central Region, the project will use 11,500 tons of material, or seven trainloads. 

This work will take place Monday through Sunday from 6 am to 6 pm until December 15th. If needed, additional man-hours may be added, but the operations manager doesn't anticipate timeline changes. 

Shelby says workers will unload the trains on Mondays, Wednesdays, and Fridays from 11 am to 3 pm. The traffic stops shouldn’t last longer than 10 minutes, but delays could occur as workers are using excavators to remove materials frozen to the cars. While other delays may occur outside this window, they should be shorter. 

This emergency project is funded by the Department of Military and Veterans Affairs. 

The state is also planning a future project with the Matanuska-Susitna Borough and the Alaska Railroad to implement more significant erosion mitigation under a broader scope, with more available funds. 

For more information as the project progresses, DOT will post updates as they’re available on[ 511.alaska.gov](http://511.alaska.gov/?ref=ktna.org).