Su Valley High School projected completion is December
[slideshow id=6]The new Su Valley High School construction has not been without its setbacks. Robert Scott, Mat Su Borough site manager for the school, says he is now breathing a
[slideshow id=6]The new Su Valley High School construction has not been without its setbacks.
Robert Scott, Mat Su Borough site manager for the school, says he is now breathing a sigh of relief. The issues with the gymnasium floor are resolved and progress is being made on that front. Scott said that there have been problems up to now with preparation of the floor. Part of the issue had to do with correct ambient conditions to get the base prepared. The effort to finish the gym ABOVE the floor is complete. The acoustical panels, climbing ropes and rolling partition curtain were finished two weeks ago.
Scott says the classrooms are finished. Work is progressing on the hallways, commons area and music room. He says that one of the most amazing features will be the lighting in the hallways. The building is a LEED building with new technology integrated into many features.
The December turnover from the contractor to the Borough is on track at this point. Scott took a group of moving company bidders on a tour last week. He expects that the school district will open the bidding process soon and a company to move the school from the portables into the new building will be chosen in November.
The two track meets held behind the school in September and October caused the contractor delays and money. One individual drove over the topsoil and down the bike path at one point, causing damage. Smudges on windows and people walking on the topsoil meant backtracking on some final inspections.
Otherwise, all the signs point to moving in on time. Scott assures the community that the building looks great and people will love the new facility with its artwork and new technology.
Note: all photos are courtesy of project manager, Robert Scott, at the Mat Su Borough
Read More
KTNA App Update: Refined Experience & Enhanced Reliability
We’ve just rolled out a significant update to the KTNA mobile app to ensure a smoother, more premium experience for every listener.
Susitna Writer Voice - July 19, 2026, One Line at a Time, bookclub poetry.
The next Susitna Writers Voice will take us through the seasons with 4 “one line at a time” collaborative poems written by a local bookclub. This piece was produced by
Welcome to the New KTNA Site
Explore KTNA’s newly redesigned website, featuring easier navigation, improved access to live radio and recent broadcasts, and clearer ways to find local news, community updates, programs, and station information.
Yaks Run Loose on Talkeetna Spur Road
At least twice this summer, yaks have been spotted running loose along the Talkeetna Spur Road. Mat-Su Borough Animal Control has opened a case for multiple reports about the loose